DOTX-45 Dissolved Oxygen System Part 10– Troubleshooting
DOTX-45 57 -
While the sensor is disassembled for membrane changing, examine the condition
of the o-rings on both ends of the electrolyte canister. If the o-rings show any
signs of damage, replace them with new ones from the spare parts kit. It is good
practice to change these o-rings once a year, regardless of their condition.
9.31 Lead Anode Replacement
Galvanic D.O. sensors consume the lead electrode during normal
operation. As oxygen is measured, lead is converted to lead oxide, and
after a period of time, the lead is expended. The lead electrode in the
D.O. sensor cartridge can be easily replaced, and replacement should be
done automatically every 12 months.
The lead electrode is the thick lead wire wrapped around the sensor body.
It is connected through a stainless steel post with a nut and star washer.
To change the lead electrode, remove the nut and washer and unwrap the
old lead. Loop the end of a new lead electrode around the post and
replace the nut and washer. Tighten the nut firmly but do not over tighten
as damage to the sensing module can result. Wrap the remainder of the
lead around the sensor body. There is no need to secure the other end of
the lead.